New construction has been completed in Rheinbach
As planned, the keys for the new production hall and the administrative building were handed over on 30 March 2016.
With the building construction complete, the requirements for the workday need to be implemented. The installation of the entire communication technology (telephone, EDP), the construction of the new warehouse and installation of cranes is taking place. At the same time a new five-stage press is being set up and put into operation.
The final move to Rheinbach is performed area by area to avoid an impact on the daily operations:
- 06.05. – 07.05.2016 The administration moves with all office workstations.
- 06.06. – 26.06.2016 production relocation. This is staged, adjusted to the individual production areas preventing production losses.
- 06.06.2016 beginning of relocation of warehouse, receiving, shipping and final assembly. At this time Bonn or Rheinbach will not accept deliveries or perform any shipments.
- Expected 01.08.2016 all rework will be completed and the daily work will go on in Rheinbach.